Road project issue dominates Sylva commission race
The race for a seat on Sylva’s town board is competitive this year, with six people running for election to one of the three open seats. Two of them are incumbents, one is a former town commissioner and three are seeking elected office for the first time. Serving four-year terms extending through December 2023, the winners will govern during a pivotal time in Sylva’s history.
Shape of N.C. 107 plans set, DOT says
The time to tweak plans for Sylva’s controversial N.C. 107 project is past, residents were told during a well-attended town meeting Thursday, Sept. 12.
TWSA discusses ways to soften N.C. 107 impacts
With right-of-way acquisition for the N.C. 107 project in Sylva set to begin in January, the Tuckaseigee Water and Sewer Authority is hoping to adopt new policies this December aimed at assisting ratepayers impacted by the endeavor.
Public protests N.C. 107 plans at town meeting
Nearly a year to the day since a standing-room-only crowd filled Sylva Town Hall for a forum on the proposed N.C. 107 project, a town meeting Thursday, Aug. 8, drew a full house of folks determined to speak out against the road during the meeting’s public comment section.
N.C. 107 relocation list still includes 55 businesses
Based on information presented at a joint government meeting in Jackson County July 23, The Smoky Mountain News reported in its July 31 issue that an updated list of businesses slated for relocation as a result of the N.C. 107 project in Sylva now numbered 39, not the 55 businesses and organizations named in the preliminary plans released last year.
Updated relocation list released for N.C. 107 project
CORRECTION: Due to inaccurate information presented at the July 23 government meeting when the road project was discussed, the number of businesses slated for relocation in the story is incorrect. The project will require relocation of businesses located on 39 parcels of property, but the total number of businesses on those parcels is 55. The list of businesses included with the story names all 55 businesses.
The number of businesses to be displaced by the upcoming N.C. 107 project in Sylva could be fewer than the 54 named in last spring’s preliminary plans, but the cost and duration of the project will be greater than initially expected, according to an update N.C. Department of Transportation Division Engineer Brian Burch gave to an assemblage of Jackson County’s elected leaders last week.
2013: Southern Loop scrapped for good
For a road that has never existed, the infamous Southern Loop of Sylva sure has gotten a lot of ink over the past 20 years.
DOT design for N.C. 107 ‘best option’ volunteer planners say
The Asheville Design Center will soon complete its final recommendations for the N.C 107 project in Sylva, but the document is unlikely to provide any drastic departure from the plan already put forward by the N.C. Department of Transportation.
Asheville Design Center to present recommendations for N.C. 107
The Asheville Design Center will present its findings on alternatives to the current plan for N.C. 107 in Sylva during a community meeting 5:30 to 7 p.m. Wednesday, April 17, at the Jackson County Public Library.
Déjà vu: N.C. 107 planners struggle to find solutions to road dilemma
After taking input from the more than 100 people who attended a Jan. 14 public forum and carefully combing their suggestions for the upcoming N.C. 107 makeover in Sylva, the Asheville Design Center generated a respectably long list of design alternatives to investigate.