Canton bridge work finished ahead of schedule

Written by 

Traffic headaches caused by bridge work in downtown Canton for the past nine months are now over.

Detour signs were taken down Monday, marking the end of the $3.5 million project to replace the 1920s-era Park Street bridge over the Pigeon River.

 

“The last of the traffic barrels will be pulled up the first of September,” said John Herrin, project manager with Taylor and Murphy Construction, which performed the bridge work.

The project is finishing nearly three months ahead of schedule.

Downtown Canton has parallel one-way streets: Main and Park. While the Park Street bridge was being rebuilt, a dog-leg detour routed traffic from Park Street over to Main Street, which was reconfigured to handle a single lane of traffic in both directions for a short section.

— By Becky Johnson

blog comments powered by Disqus
Read 1526 times Last modified on Thursday, 23 August 2012 18:51

Media

blog comments powered by Disqus

This Must Be the Place

  • This must be the place

    art theplaceWhen the camera bulb flashed, it hit me — had it really been that long?

    Standing in the Belhurst Castle, a Great Gatsby-esque property situated on Seneca Lake in Geneva, N.Y., I realized it had been around a decade since my childhood friends and I had been in the same room together. And yet, here we were, drinks in hand, smiles plastered across our faces, as family members and dates for the wedding stood in front of us, eager to capture the moment we all were huddled as one.

    Written on Wednesday, 30 July 2014 13:33 Read more...